The post Construction Update July 30, 2015 appeared first on North Shore.
]]>
NOTE: Once we finish the land disturbing activities on this side of our project, this storm water pond will be converted to a bio-retention facility with special soil and plants for permanent application
.
Aug 15
While progress continues on site, we had a great official ground breaking today. Check the pics of all the fun and work!
Oct 12
Rain has ended and site work continues! Construction on the alley behind the first building and the parking lot for the pool has begun. Retaining walls for pool to start tomorrow.
Dec 10
Site work continues. The first below slab plumbing was approved today. The concrete slab team will be on site this coming Monday. If all goes well and weather permitting, framing will begin Monday Dec 21!!

The post Construction Update July 30, 2015 appeared first on North Shore.
]]>